Project Description
The project limits consist of Alfred Street East from the O’Brien Street North to Angus Campbell Drive.
The anticipated scope of works include asphalt removal and replacement, shouldering, ditching, driveway/entrance reinstatements, landscaping reinstatement, and line painting.
Traffic Impacts
Traffic disruptions and detours may occur.
Status
Ongoing.
Schedule
Asphalt removal and replacement works will commence the week of July 8 and all project works are anticipated to be completed by early August.
Project Contact
Paul Champagne
Supervisor of Roads & Fleet
613-735-6821 ext. 1415